Rebuilding Plan and Schedule
 Removing the trusses on the South Hall, October 11, 2007.

 |
Mayor Fenty has committed the full efforts of the District Government to restoring this landmark building as quickly as possible. The temporary East Hall and the weekend outdoor market is open for business.
- Fire Cleanup
Complete (May 2007)
- East Hall
Vendor Move-in Date: Complete (August 2007) Public Opening: Complete (August 25, 2007)
- Design for Renovations and Rebuilding
Revised Renovation Bid Package: October 2007
- Permanent Roof Installation
Design (with approval of Historic Preservation Review Board, US Commission on Fine Arts, National Capital Planning Commission, Office of Contracting and Procurement): Complete (July 2007) Mayor and DC Council Approve contract over $1 million – Complete (October 4, 2007) Receive notice of Council Approval – (Complete) October 22, 2007 Award Contract – October 22, 2007 South Hall Roof Completion: July 2008 North Hall Roof Completion: TBD depending on Council approval of contract
- Window Replacement
Award Contract: December 7, 2007 Completion: July 2008
- Interior Market Renovation
City Council Review and Approve contract over $1 million – Complete (April 10, 2008) Award Contract – Notice to proceed May 5, 2008 Final Completion and Reoccupation: Summer 2009
- Full Building Renovation Completion: June, 2009
|
|
|